Object nameStageBeginningEnding
Ferrexpo Poltava Mining PJSC. Technical re-equipment of the fine screening department on sections No.10-15 in the building of the beneficiation building with the storage of concentrate No.2 of the crushing and beneficiation factory. Installation of fine screening screens on sections No.10-11.Detail Engineering05.202009.2020
Ferrexpo Poltava Mining PJSC. Technical re-equipment of the magnetic separation stage at technological sections of Beneficiating Factory No1. Provision of technical water and tailings removal during the restoration of the first stage of magnetic separation with a simultaneous increase in production capacity for processing source ore.Feasibility Study03.202006.2020
Ferrexpo Poltava Mining PJSC. New construction of the complex of the first stage of ore crushing. The major crushing complex (MCC-3).Feasibility Study11.201902.2020
Zaporizhzhya Iron Ore Plant PJSC. Installation of an oil lubrication system for mills in the laying area.Final Documents10.201912.2019
Zaporizhzhya Iron Ore Plant PJSC. Installation of an oil lubrication system for conveyors No.90 and No.94.Final Documents10.201912.2019
Central GOK PJSC. Correction of the main technological indicators for the crushing and beneficiating complex.Scientific Research09.201911.2019
Ferrexpo Poltava Mining PJSC. Pelletizing Factory. Technological line No. 2. Installation of a leveling wall with the replacement of the smoke exhaust and its piping.Detail Engineering08.201910.2019
Ferrexpo Poltava Mining PJSC. Pelletizing Factory. Reconstruction of the loading hopper.Detail Engineering08.201912.2019
Ferrexpo Poltava Mining PJSC. The construction of sections for screening fired iron ore pellets on the shipment paths No. 1 and No. 2.Feasibility Study08.201911.2019
Ferrexpo Poltava Mining PJSC. Reconstruction of the administrative building.Basic Engineering and Final Documents08.201903.2020
Ferrexpo Poltava Mining PJSC. Pellet Production Workshop. Construction of a new pelletizing building for the production line No. 4.Basic Engineering and Final Documents07.201912.2020
Central GOK PJSC. Automated process control system for the production of concentrate on the beneficiating factory for DRI technology. The upper level of the process control system.Final Documents07.201911.2019
Ingulets GOK PJSC. Beneficiating Factory No. 2. Installation of hydrocyclones of the Multotec company.Detail Engineering06.201909.2019
Ferrexpo Poltava Mining PJSC. Mining workshop. Technical re-equipment of the sound alarm system of imploding works.Detail Engineering08.201911.2019
Ferrexpo Poltava Mining PJSC. Pellet Production Workshop. Construction of a new pelletizing building for the production line No. 1.Basic Engineering and Final Documents06.201911.2020
Ferrexpo Poltava Mining PJSC. Pellet Production Workshop. Reconstruction of a pelletizing site to ensure industrial testing of a pelletizing disc with a diameter of 7.5 m using a buffer tank building.Basic Engineering and Final Documents06.201912.2019
Northern GOK PJSC. Development of monitoring tools to improve the quality of electric energy in the networks of the enterprise.Scientific Research, Detail Engineering02.201905.2019
Development and implementation of rational scientific, technical and design solutions to reduce the enterprise’s fee for reactive power and minimize losses in the power supply networks of networks and substations.Scientific Research06.201909.2019
Ferrexpo Poltava Mining PJSC. Installation of XR-400 pumps (2 pcs.) For transferring the tailings of the regrinding site of the 1st flotation of Crushing and Beneficiating Factory No. 2 to the tailings of Crushing and Beneficiating Factory No. 1.Final Documents01.201906.2019
Northern GOK PJSC. Increasing the iron content in the concentrate using flotation finishing technology at Severny Mining PJSC in order to achieve a mass fraction of total iron in magnetite concentrate of at least 69.0%.Feasibility Study01.201909.2019
Ferrexpo Poltava Mining PJSC. Pelletizing Factory. Installation of a pendulum beam on a drum pelletizer.Detail Engineering10.201811.2018
Ferrexpo Poltava Mining PJSC. Technical re-equipment of the magnetic separation stage at the technological sections of Ore and Beneficiating Factory No. 1.Feasibility Study01.201906.2019
Central GOK PJSC. Reconstruction of DRI pellet concentrate production line.Basic Engineering and Final Documents09.201804.2019
Northern GOK PJSC. Updating the design documentation of the Ore and Beneficiating Factory No. 1.Basic Engineering10.201804.2019
Northern GOK PJSC. Software development for calculating the material stock of charge materials in the manufacture of pellets for roasting machines.Scientific Research09.201811.2018
Ferrexpo Poltava Mining PJSC. Building of Press Filter Сonstruction. Transfer of drainage pumps from the press filtration construction area.Final Documents08.201811.2018
Central GOK PJSC. Pelletizing Factory. Installing a SCARABAEUS 7500 Peletizing Disc instead of an existing pelletizer on line No. 74.Detail Engineering07.201809.2018
Central GOK PJSC. Pelletizing Factory. Reconstruction of the sorting site for roasting pellets in order to exclude the +16.0 mm class from finished pellets.Detail Engineering06.201808.2018
Ferrexpo Poltava Mining PJSC. Pelletizing Factory. Technological line No. 2. Installation of a leveling wall with the replacement of the smoke exhaust and its piping.Detail Engineering05.201807.2018
Ferrexpo Poltava Mining PJSC. Pelletizing Factory. Technological line No.1. Reconstruction in order to increase productivity from 3.0 to 6.5 million tons/year for finished pellets.Feasibility Study08.201802.2019
Ferrexpo Poltava Mining PJSC. 9th section. Power supply 6 kV.Check Final Documents05.201808.2018
Ingulets GOK PJSC. Crushing Factory. Site 3-4 stages of crushing. Reconstruction of the lubrication area.Detail Engineering04.201809.2018
Ferrexpo Poltava Mining PJSC. Pelletizing Factory. Building of Press Filter Сonstruction. Calculation of short circuit currents and settings.Detail Engineering04.201806.2018
Kryvyi Rih International Airport. Installation of block Complete Transformer Substation.Detail Engineering01.201803.2018
Lebedinsky GOK JSC. Pelletizing Factory. Roasting case No. 2. Reconstruction of the system of flow-transport system of roasting machines.Author’s supervision, Final Documents01.201810.2018
RUDOMAIN LLC (Kryvyi Rih). Development of technological regulations for the beneficiation of hematite quartzites of the mine named after Kirov (mine field named after Artyom) using dry magnetic separation technology to obtain marketable products at facilities located at ul. Dzhambula, 33/1 and st. Ionova Balka, 15/a2.Laboratory research, Scientific Research12.201702.2018
Ferrexpo Poltava Mining PJSC. Pelletizing Factory. Reconstruction of the pelletizing site to ensure the implementation of Industrial research of a Pelletizing Disc with a diameter of 7.5 m.Predesign Study12.201701.2018
Ferrexpo Poltava Mining PJSC. Laboratory and pilot tests for pelletizing “Premium” and “Premium+” concentrates at the HAVER Engineering GmbH research laboratory.Scientific Research04.201808.2018
Regional communal manufacturing enterprise “Dnipro-Kirovograd”. Reconstruction of sewer pumping (20 objects)Basic Engineering and Final Documents. Author’s supervision11.201710.2018
Ferrexpo Poltava Mining PJSC. Pelletizing Factory. Development of technological regulations for the beneficiation of substandard ores of the Krivoy Rog iron ore basin.Feasibility Study, Basic Engineering and Final Documents09.201709.2018
Ferrexpo Poltava Mining PJSC. Pelletizing Factory. Technological line No. 1. Installation of an additional crane.Predesign Study07.201707.2017
Ferrexpo Poltava Mining PJSC. Pelletizing Factory. Technological line No. 1 and No. 4. Reconstruction of the pelletizing site in order to increase productivity up to 6.5 million tons/year for finished pellets.Predesign Study06.201706.2017
Shimanovskoye Steel LLC. Analytical review of the possibility of processing ores of the Shimanovsky deposit at the mining and mining plants of Ukraine.Scientific Research04.201704.2017
Ferrexpo Poltava Mining PJSC. Beneficiating Factory No. 2. Construction section No.16. Productivity 5.6 million tons/year for source ore.Development of the technological task, Feasibility Study03.201710.2017
RUDOMAIN LLC (Kryvyi Rih). Development of technological regulations for the processing of substandard ores of the Krivoy Rog iron ore basin.Scientific Research02.201702.2017
KMAruda Combine OJSC (Russia). Development of technology for the beneficiation of magnetite quartzite. Construction of a Beneficiating Factory with a productivity of 7.0 million tons/year for source ore.Prefeasibility Study, 3D model in two versions10.201602.2017
Boryspil International Airport State Enterprise. Reconstruction of tank RVS-1000 No. 1,2,3 and RVS-2000 No. 4,5Author’s supervision09.201612.2016
“Sokolovsko-Sarbaisky mining and processing production association” OJSC (Kazakhstan). Development of technology and technological solutions for the reconstruction of a Beneficiating Factory with a productivity of 45 million tons/year.Prefeasibility Study, 3D model08.201610.2016
Atlas Copco LLC. Reconstruction of the workshop with the installation of a crane beam with a payload of 16 tonnsDetail Engineering03.201605.2016